This is the part where the real progress began to happen! We filed our plans with the Department of Buildings for review in December 2019. We were denied five times, and by March 20, 2020 for the sixth review, we requested a new examiner and were finally approved for a construction permit. Then the pandemic hit. The city stopped all construction work the exact week we scheduled our contractor to begin. Another three months trickled by before we finally got our work permit. Honestly with the bigger picture of the pandemic unfolding around us at that time, we needed to reflect.
Amy and I thought that we could save the walls. Just rewire, add new paint, and new floors and we’d be good. The trouble was that the floor was sagging so severely that my contractor needed to find out what was happening with them. After opening the walls at every floor joist, his team discovered half the joists were only resting 1/2″ inside the wall pockets. Between that and the fact that someone poured a 4″ concrete slab in the middle of the floor where the bathroom was, it was no wonder the floor deflected up to 5″ at the center.
So the second floor was about to collapse. That’s when my contractor suggested we gut everything because he was going to need to replace all the floor joists. I thought it would be nice having level floors that didn’t bounce, so we agreed to go for it.
The first floor
After the second floor was clean, it was time to fill up more dumpsters with the first floor. Again, Amy and I were hoping to save some walls, but we ran into the same problems with the floor. Not as severe as the second floor, but enough to justify a clean out.
The basement
I was planning to demo the basement later and only concentrate on the first and second floors for now. But after the terrible condition my contractor exposed on the top two floors, we went ahead and tackled the basement demo. The floors on the basement level were sagging too and they felt really unstable. The plan was to salvage the joists we could, then sister the rest (add 2×6 boards alongside the floor joists to get them all level). Then add a nice new 3/4″ plywood sub floor.
The demolition phase lasted about three months because we had to be careful what could be removed and when. My contractor also replaced the floor beams as his crew worked their way down to ensure the house would not implode. This is the tricky part about working on old Victorian era houses that were not taken very good care of. You need to think three steps ahead before jack hammering; otherwise, it could lead to disaster.